Septic Drain Field Size Calculator

Estimate the absorption area and trench layout from design flow and your local soil loading rate.

Use the loading rate from a local soil evaluation or permitting table. Example values are not permit defaults.

gpd
Use the value required by the local code or designer.
gpd/ft²
Enter the approved rate in gallons per day per square foot.
ft
ft
%

Calculation method

How drainfield area is estimated

Daily design flow equals bedrooms × design flow per bedroom. Minimum infiltrative area equals daily design flow ÷ the local soil loading rate; trench length equals area ÷ trench width.

Codes can require additional area, specific trench products, pressure distribution, or a full replacement field. Enter the local values instead of treating this model as a national rule.

Worked example

Septic field size and absorption trench calculations

The calculator keeps design flow, soil loading rate, trench width, lateral length, and reserve area separate so each local assumption remains visible.

Daily flow = bedrooms × design flow per bedroom Absorption area = daily flow ÷ soil loading rate Total trench length = absorption area ÷ trench width

Example: three-bedroom planning layout

At 120 gpd per bedroom, design flow is 360 gpd. With a local loading rate of 0.60 gpd/ft², the minimum infiltrative area is 600 ft². At a 3 ft trench width, total trench length is 200 ft.

With a 100 ft maximum lateral, that example needs at least 2 laterals. A 100% replacement reserve protects another 600 ft², for 1,200 ft² total.

Sources and references

Reviewed July 28, 2026. Local permit rules and official records override planning values. How we select and review sources.

FAQ

Drainfield sizing FAQ

Can I use a perc rate directly?

Only after converting it through the loading-rate table required by your local authority. Perc rate and soil loading rate are not interchangeable.

Is this enough for a permit?

No. Site evaluation, setbacks, seasonal water table, slope, reserve area, and system type still require professional review.